September 5, 2006 - Completed

 

Special Reclamation of the following streets and/or alleys:

 

1. Fenwick Drive

2. Fenway Drive

3. Wadxwing Circle

4. Weatherly Drive

5. Richfield Drive

6. Richfield Street

7. Parkcrest Drive

 

 

Full-Depth Reclamation (FDR) of the following streets:

 

1. Winfield Boulevard

2. Fourwinds Drive

3. Midcrown Drive

 

 

August 21, 2006 - Completed

 

Mill and Overlay on the following streets:

 

1. Fourwinds Drive

2. Crosswind Drive

 

September 5, 2006 - Completed

 

New Alley Approaches to the following alley-ways:

 

1. Waxwing Drive

2. Richway Drive

3. Richfield Street

4. Richfield Drive

5. Richfield Lane

Windcrest Capital Improvement Project

Scheduling -- In Progress

Sche